CONSTRUCTION OF TWO HEATING PLANTS
Implementation started in March 2020.
ENERGAN-95 OOD IS A SUBCONTRACTOR TO POWER ENGINEERING STARA ZAGORA
UNDER THIS PROJECT, STOPPING AND REGULATING FITTING WILL BE DELIVERED IN THE PERIOD 03-08.2020 SUCH AS: butterfly valves, stop valves, gate valves, ball valves, non-return valves, balance valves, regulating valves with direct action and electric actuator, breathing valves, shut-off valves gas valves.
CONSTRUCTION OF A FLUE GAS CLEANING INSTALLATION
ENERGAN-95 OOD SUPPLIES STOP FITTING:
- BUTTERFLY VALVES,
- GATE VALVES,
- BLADES,
- SOLENOID VALVES
Deliveries are made in the period: June-August 2020.
PROJECT FOR BROW 140/15 FOR THE CITY OF BURGAS
The implementation started in September 2021.
COMPANY ENERGAN-95 LTD DELIVERS
- THE ARMATURE
- REDUCTION COOLING DEVICE AND THE AUXILIARY FITTINGS TO IT
- GATE VALVES AND BREATH VALVE
The fittings will be delivered in the period 03-08.2023.
DELIVERY OF FITTINGS FOR THE FLUE GAS CLEANING SYSTEM
Energan-95 Ltd. is a supplier of fittings:
- Butterfly flaps and blade flaps
Deliveries were made in the period: September-December 2022.
SUPPLY OF EXHAUST GAS DAMPERS AND DISC VALVES
Energan-95 Ltd. organizes the delivery of the dampers, produced by Swedenborg, Sweden.
Two pcs. are delivered. disc dampers 1800x1600 mm and guillotine dampers sizes D2000 - 2 pcs and D2400 - 2 pcs
Deliveries are made in the period: September 2022 - August 2023.